rus

Bottling line configuration change (straightening)

Project purpose:

  • Optimization of production space;
  • Improve of ergonomics of production operations;
  •  

Equipment to be transferred

  • Sleeve-labeler
  • Steam tunnel
  • Cardboard packer
  • Device for container turnover
  • Conveyor system
  • Printer

Specific demands: 

  • Only 72 hours of line shutdown is available; 

Works perfromed:

During production hours

  • Design of a new line configuration;
  • Preparatory work without stopping the line;

Within 72 hour line stop

  • Dismantling of equipment:
  • Moving to a new position
  • Mechanical and electrical installation
  • Wiring and piping works
  • Trial starts without product

On a running line

  • Start-up and adjustment
  • Achievement of a performance indicators as "before upgrade"